Module 1 Observations and Action Items

Stream Name Survey Date Organization Project Name Survey ID Data Entered By
WINDEBANK CREEK 2015-11-19 Mission of Streams Windebank Monitoring 84 DU

Observation Number Feature Number Photo Taken Photo Upstream from last feature Feature Description Feature Detail Feature Size Bank Affected Adjacent Land Use Action Items
1107 11 Yes 0 Bank Erosion sand/gravel deposition mid-channel in low gradient section adjacent to homeless camp (feat. 9) Large blue tarp partially buried. 30 m long x 3 m wide Mid-stream Residential Clean out garbage instream from homeless camp.
1108 12 Yes 0 Bank Erosion sand/gravel deposition mid-channel in low gradient section adjacent to homeless camp (feat. 9) Large blue tarp partially buried. 30 m long x 3 m wide Mid-stream Residential Clean out garbage instream from homeless camp.
1109 13 Yes 0 Bank Erosion sand/gravel deposition mid-channel in low gradient section adjacent to homeless camp (feat. 9) Large blue tarp partially buried. 30 m long x 3 m wide Mid-stream Residential Clean out garbage instream from homeless camp.
1110 14 Yes 0 Bank Erosion sand/gravel deposition mid-channel in low gradient section adjacent to homeless camp (feat. 9) Large blue tarp partially buried. 30 m long x 3 m wide Mid-stream Residential Clean out garbage instream from homeless camp.
1111 15 Yes 0 Bank Erosion sand/gravel deposition mid-channel in low gradient section adjacent to homeless camp (feat. 9) Large blue tarp partially buried. 30 m long x 3 m wide Mid-stream Residential Clean out garbage instream from homeless camp.
1112 16 Yes 0 Bank Erosion sand/gravel deposition mid-channel in low gradient section adjacent to homeless camp (feat. 9) Large blue tarp partially buried. 30 m long x 3 m wide Mid-stream Residential Clean out garbage instream from homeless camp.
1113 17 Yes 0 Bank Erosion sand/gravel deposition mid-channel in low gradient section adjacent to homeless camp (feat. 9) Large blue tarp partially buried. 30 m long x 3 m wide Mid-stream Residential Clean out garbage instream from homeless camp.
1114 18 Yes 0 Bank Erosion sand/gravel deposition mid-channel in low gradient section adjacent to homeless camp (feat. 9) Large blue tarp partially buried. 30 m long x 3 m wide Mid-stream Residential Clean out garbage instream from homeless camp.
1115 19 Yes 0 Bank Erosion sand/gravel deposition mid-channel in low gradient section adjacent to homeless camp (feat. 9) Large blue tarp partially buried. 30 m long x 3 m wide Mid-stream Residential Clean out garbage instream from homeless camp.
1116 20 Yes 0 Bank Erosion sand/gravel deposition mid-channel in low gradient section adjacent to homeless camp (feat. 9) Large blue tarp partially buried. 30 m long x 3 m wide Mid-stream Residential Clean out garbage instream from homeless camp.

Records 11 to 20 of 21